Frissítés(2022.10.27.): Published on 26.10.2022 Hungarian Gazette based on:
After 30 October 2022, a temporary STOP on feed-in will apply to new HMKE systems!
Government Decree 413/2022 (X. 26.):
"a small household power plant may be commissioned which produces electricity solely for the purpose of meeting its own electricity consumption, and the small household power plants so commissioned may be connected to the public grid the possibility of feeding the animals is temporarily suspended.
Small household power plants implemented on the basis of applications made before 31 October 2022 may be connected to the public grid!"
Back-wattage protection has also become increasingly important for residential solar systems. This regulation will affect those who apply to install a solar PV system after 30 October. Those who have previously notified their service provider will continue to be charged on a net metering basis.
Have you already submitted your solar application? Leave the implementation to us!

The billing system above 50 kW - For industrial customers Solar PV systems based on renewable energy are not only environmentally friendly and reduce overheads, but are also of strategic importance for the future of our company, as they have an increasingly favourable payback period.
First, let's see what is BACKWATT BLOOD? For solar PV systems above 50 kW, we are talking about systems with back-feed discharge.
These systems are no longer covered by the HMKE rules, so they balance the energy of installations with a capacity above 50 kW.
The main purpose of this system is that if the solar system is producing more power than is needed on site, it will either regulate the inverters back to instantaneous output or shut them down.
This is an optimal business and technical solution, as the solar system only generates energy when it is needed.
Important: Before installing any solar PV system, a survey and individual quotation is required.
Our experts will help you find the most optimal size and type of solar system! Our services cover the full investment process, including project management, use of grant funding, connection planning, permitting and turnkey implementation.
Request our free survey and we will find the best solution for you!